Physics, asked by sangeetadas59023, 7 months ago

what is the work to be done to increase the velocity of car from 30 h - 1 to 60 km h -1 if the mass of the car is 1500kg???????


Answers

Answered by Ekaro
13

Given :

Mass of the car = 1500kg

Initial velocity = 30km/hr

Final velocity = 60km/hr

To Find :

Work done to increase velocity of the car.

Solution :

❖ As per work-energy theorem, work done is always equal to change in kinetic energy.

Mathematically, W = k' - k

  • W denotes work done
  • k' denotes final kinetic energy
  • k denotes initial kinetic energy

Kinetic energy of body of mass m moving at a velocity of v is given by, k = 1/2 mv²

• Initial velocity = 30km/hr

  • 30 × 5/18 = 8.33m/s

• Final velocity = 60km/hr

  • 60 × 5/18 = 16.67m/s

By substituting the given values;

\sf:\implies\:W=\dfrac{1}{2}m(v^2-u^2)

\sf:\implies\:W=\dfrac{1}{2}(1500)[(16.67)^2-(8.33)^2]

\sf:\implies\:W=750(277.89-69.39)

\sf:\implies\:W=750(208.5)

:\implies\:\underline{\boxed{\bf{\purple{W=156,375\:J=156.4\:kJ}}}}

Answered by Anonymous
3

{\bold{\large{\sf{\underbrace{Question}}}}}

What is the work to be done to increase the velocity of car from 30 km/h to 60 km/h ; if the mass of the car is 1500 kg.

{\bold{\large{\sf{\underbrace{Answer}}}}}

{\bold{\large{\sf{\underline{Given \: that}}}}}

❖ Initial velocity = 30 km/h

❖ Final velocity = 60 km/h

❖ Mass = 1500 kg

{\bold{\large{\sf{\underline{To \: find}}}}}

❖ Work done.

{\bold{\large{\sf{\underline{Solution}}}}}

❖ Work done = 156375 Joules

{\bold{\large{\sf{\underline{Understanding \: the \: question}}}}}

❖ This question says that their is a car its mass is 1500 kg. It's initial velocity and final velocity is given as 30 km/h and 60 km/h respectively. Afterwards this question says that we have to find the work to be doned.

{\bold{\large{\sf{\underline{Knowledge \: required}}}}}

❖ According to the work energy theorm's = Work doned is always equal to kinetic energy change. That's why mathematically using rule is, {\bold{\sf{W \: = \: k^{1} \: - \: k}}}

Where the values,

{\sf{W}} means work doned

{\sf{k^{1}}} means final kinetic energy.

{\sf{k}} means initial kinetic energy.

❖ Kinetic energy –

{\large{\green{\bf{\boxed{Kinetic \: energy \: = ½ \: mv^{2}}}}}}

{\bold{\large{\sf{\underline{Using \: concept}}}}}

❖ Work doned.

{\bold{\large{\sf{\underline{Using \: formulas}}}}}

{\large{\green{\bf{\boxed{Work \: done \: = \: \frac{1}{2}m(v^{2} - u^{2}}}}}}

{\bold{\large{\sf{\underline{Full \: solution}}}}}

{\green{\bf{\boxed{Work \: done \: = \: \frac{1}{2}m(v^{2} - u^{2}}}}}

{\green{\bf{\boxed{Work \: done \: = \: \frac{1}{2}(1500[(16.67)^{2} - (8.33)^{2}]}}}}

{\green{\bf{\boxed{Work \: done \: = \: 750(277.89 \: - \: 69.39)}}}}

{\green{\bf{\boxed{Work \: done \: = \: 750(208.5)}}}}

{\green{\bf{\boxed{Work \: done \: = \: 750 \times 208.5}}}}

{\green{\bf{\boxed{Work \: done \: = \: 156375 \: Joules}}}}

Similar questions