What is used to illustrate precedene relationships in AOA network?
(A) Raw activity
(B) Dummy activity
(C) Pseudo activity
(D) Null activity​

Answers

Answered by Fatimakincsem
2

A dummy activity is used to illustrate the precedence relationship n AOA in the network.

Option (b) is correct.

Explanation:

  • In order to construct a Network, a precedence relationship is always used to demonstrate the direction from left to right.
  • There are nodes in the network and they are represented y numbers 1,2,3 and so on.
  • In order to represent the relationship dummy activities are used in place of actual activities in the project as they are easy to use and have zero completion time.

Answered by khwatinkijannat
0

Answer:

dummy activity

Explanation:

used to illustrate preceden relationship in aoa network