What network model enables the engineer managers to schedule monitor and control large and complex projects by employing three time estimate for each activity

Answers

Answered by poonamdevi1743
0

Answer:

The 'network model' which enables 'engineer managers' to monitor, schedule, and control large and 'complex projects' by using only 'one-time factor' per activity is 'Program evaluation review technique'.

Answered by dharanikamadasl
0

Answer:

The network model enables the engineer managers to schedule monitor and control large and complex projects by employing the time estimation for each activity Program Evaluation and Review Technique (PERT).

Explanation:

  • Program Evaluation and Review Technique (PERT) is a statistical project management tool designed to analyze and present tasks related to the implementation of a particular project.
  • PERT is a method of analyzing the tasks related to the completion of a particular project, specifically the time required to complete each task, and determining the minimum time required to complete the entire project.
  • Uncertainty is associated with being able to plan a project without knowing the exact details and duration of all activities.
  • This is an event-focused approach rather than a start-and-complete approach and is more likely to be used in projects where time is more important than cost.
  • This applies to very large, one-off, complex, typical infrastructure, and R & D projects.

Hence, the Program evaluation and review technique is used by the engineer managers.