. What will be the earnings of a
worker at 60 paise per hour when he
takes 100 hours to do a volume
of work for which the standard time
is 160 hours the plan of payment for
bonus is on a sliding scale
as under:
Within the first 10% saving in the
Standard time, the Bonus is : 40% of
the Time Saved.
Within the second 10% saving in the
Standard Time, the bonus is : 50% of
the Time Saved.
Within the third 10% saving in the
Standard Time, the bonus is : 60% of
the Time Saved.
Within the Fourth 10% saving in the
Standard Time, the Bonus is : 70% of
the Time Saved.
For the rest of the time saved : 75% of
the Time Saved.
9:42 pm
Answers
Answered by
2
Answer:
Explanation:
answer is 79.44