Math, asked by purnasingh3007, 1 year ago

When a,b,c are work together they complete a job in 8 days. When a and c decided to do the work together they completed this job in 12 days. In how many days b alone can complete the work?

Answers

Answered by GauravSaxena01
1
Solution:-

A B and V complete the total work = 8 days


A +B +C = 8 Days ----------- (i)

Work rate of (A +B +C) = 100/8
= > 12.5 % per day.

A and C complete the total work in 12 day's

A +C = 12 days ------------ (ii)

Work Rate of (A +C) = 100/12
= > 8.33% per day.

Work Rate of B,

= (A +B +C) - (A +C)

= > 12.5 - 8.33
= > 4.16% per day.

Therefore B can complete the remaining work alone

= > 100/4.16 = 24 days.

=============
@GauravSaxena01