Business Studies, asked by nazirhaq4703, 10 months ago

When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as

Answers

Answered by Anonymous
0

Explanation:

Any activity or task on the critical path has zero float. That is, you can't delay it at all without causing a delay in the project or dependent tasks. However, there are plenty of other activities in the project that can be delayed

Answered by bastakotinaresh081
1

Answer:sub critical patha

Explanation: according to RK shreshtha nepali writer

Similar questions