When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as

Answers

Answered by Anonymous
0

Explanation:

Any activity or task on the critical path has zero float. That is, you can't delay it at all without causing a delay in the project or dependent tasks. However, there are plenty of other activities in the project that can be delayed

Answered by bastakotinaresh081
1

Answer:sub critical patha

Explanation: according to RK shreshtha nepali writer