When they work alone, B needs 25% more time to finish a job than A does. They two
finish the job in 13 days in the following manner: A works alone till half the job is done, then
A and B work together for four days, and finally B works alone to complete the remaining
5% of the job. In how many days can B alone finish the entire job?
Answers
Answer:
B alone can finish the job in 16 days
Step-by-step explanation:
Let A finishes the work in x days
A in 1 day does = 1/x work
B finishes the work = x + 0.25x = 1.25x days
B in 1 day does = 1/1.25x work
A does half the work in x/2 days
Reamining job = 50%
B alone does 5% of the job
Therefore, A and B in 4 days did = 45% of work
Thus
Therefore, B alone can finish the job in 16 days
Answer:
B alone can finish the entire job in 20 Days
Step-by-step explanation:
Let say A complete the job in A Days
Then B completes the job in B Days
B needs 25% more time to finish a job than A
=> B = A + (25/100)A
=> B = 1.25A
A's 1 day work = 1/A
A works alone till half the job is done = 1/2
=> Number of Days A worked = A/2
A and B work together for four days
B works alone to complete the remaining 5% of the job
Work done by B alone = (5/100) = 1/20
Number of Days B worked = B/20 = 1.25A/20 = 0.0625A
A/2 + 4 + 0.0625A = 13
=> A + 0.125A = 18
=> A = 16
B = 1.25A = 16 * 1.25 = 20
B alone can finish the entire job in 20 Days