Which figures would help your audience to recapitulate the completed points before moving on to the next points.
Answers
Answered by
3
Answer:
My understanding is that not finished items for a moment go back to the product backlog and product owner decides again what to take to the next sprint. There could be cases where not finished are not taken to a sprint. So we should re-estimate the effort which is left so we have a clear situation in the backlog. Estimations are not for keeping historical data. We have also quite clear situation in the new sprint that the sum of estimation is valid - we really see how much effort is planned for that sprint