Which of project management techniques is deterministic in nature?

Answers

Answered by prachibehera
1

There are various types methods involved in displaying and analysis project schedules deterministic scheduling is the most commonly used scheduled technique..... The values scheduled direction start and finish date activities are deterministic in nature

Hope its helpful to u

Answered by Sahil3459
0

Answer:

Deterministic scheduling involves a variety of ways for visualising and analysing project schedules. CPM technique is deterministic in nature.

Explanation:

The critical path method (CPM) is a method for determining schedule flexibility and identifying tasks required for project completion. The longest series of tasks that must be completed on schedule for the project to be concluded is known as a critical path in project management. This project plan for building a house is a condensed illustration of critical path project management. The Work Breakdown Structure (WBS) contains a list of all the project's tasks, together with information about how they are related to one another and how long they will take to complete.

How do you calculate CPM in project management?

The following equation is used to determine the Early Start and Early Finish dates:

Early Start of the activity = Early Finish of predecessor activity + 1

Early Finish of the activity = Activity duration + Early Start of activity – 1

Thus, the Critical Path Method, sometimes known as CPM, is an algorithm used in project management to plan out project tasks.