Which of the following Agile Metrics is not part of cost and schedule?
1. Release Burnout Performance Indicator
2. Running Tested Features
3. Risk Slippage Risk Indicator
4. Story Point Effort Performance Indicator
Answers
Answered by
10
Answer:
Answer 4
Explanation:
Hope it will help you
Answered by
4
Answer:
Story Point Effort Performance Indicator IS not a part.
Explanation:
Agile metrics provide insight into productivity through the different stages of a software development lifecycle. This helps to assess the quality of a product and track team performance. Metrics are a touchy subject.