Computer Science, asked by ermilanawasthipcrloq, 1 year ago

which of the following can be used to track the tasks of a project when the estimation of task time is fairly uncertain?
(a) decision table
(b) case tools
(c) DFD
(d) PERT

Answers

Answered by pulkit100
0

decision table is ans

Answered by phillipinestest
0

PERT can be used to track the tasks of a project when the estimation of task time is fairly uncertain.

The full form of PERT is Project Evaluation and Review Technique. When planning and designing the project the role of PERT chart is very important. It can determine the critical path of a project from start till the finishing time of the project.