Which of the following doesn’t represent an issue Material Requirement Planning element?
Answers
Answered by
5
Answer:
Production Order.....
Answered by
0
D. Production Order doesn’t represent an issue Material Requirement Planning element.
Material Requirement Planning element (MRP):
- MRP systems depend on four essential types of data to identify what needs to be bought.
- Manufacturing schedules, material specifications, production cycle periods, and supplier lead times are among the four sources of information.
Production Order:
- A production order is a company-issued order to produce a certain quantity of material within such a specific period.
- A production order specifies which material is to be processed, where it is to be processed when it is to be handled, as well as how much quantity is necessary.
- It also specifies which parts and sequence of operations will be employed, as well as how order costs will be handled.
- Planned orders are the end consequence of using MRP.
Complete question:
Which of the following doesn’t represent an issue Material Requirement Planning element?
A. Sales Order
B. PIR
C. Transfer Order
D. Production Order