Business Studies, asked by atigga100, 7 months ago

Which of the following is not a reason to reduce
project completion time?
1)reduce new product development
2)release resources for other products
3)avoid penalties for late completion
4)eliminate project is critical path

Answers

Answered by Lokanshchuhan
3

Answer:

3) avoid penalties for late completion

Answered by ritubhatt081984
2

Answer:

3rd one is the correct answer

Similar questions