Which of these BEST describes the approach for determining the sprint length in scrum
Answers
Answered by
6
Answer:
Sprint length should not be more than month. Ideal sprint length should be for 2 weeks.
Explanation:
Shorter length provide opportunity to work closely and release many more feature to customer.
Answered by
3
There is no one-size-fits-all, for determining a sprint length that works well for every team.
Explanation:
The following elements play a critical part when any team is trying to determine sprint lengths in a scrum.
- The expected duration of the project
- Customers/stakeholders
- How often can they provide feedback and guidance
- Scrum familiarity
- The cultural barriers existing in the company or with the stakeholder/customer group
- Environmental factors
- The Scrum team
- Scrum experience
- Technical capabilities (such as automated acceptance testing, TDD, automated releases, etc.)
- Ability to decompose work