Business Studies, asked by vishakhasahni20, 1 year ago

which one is true for statistical process control (SPC)?
Ans.
Options: A. SPC is employed to control statistics of machine operations
B. SPC provides data for inventory management
C. SPC uses conrol charts to identify process correctness
D. SPC provides job scheduling statistics

Answers

Answered by captainkhan85
2
Option A is correct.
SPC is employed to control statistics of machine operations.
Answered by Sidyandex
9

C. SPC uses control charts to identify process correctness.

SPC is used for measuring and controlling the quality during a manufacturing process.

During manufacturing, quality data can be obtained for measuring and controlling the quality.

This information is plotted on a graph with pre-determined control limits and variations are identified.

If data falls within the control limits then everything is considered to be normal but if it falls outside the control limits, it can indicate the cause of the variation and necessary steps can be taken to fix it.