Which provides the sponsor or customer with an independent assessment of project progress?

(A) Project summary

(B) Project details

(C) Project audit

(D) Project plan​

Answers

Answered by neeraj559145
1

Answer:

C) Project audit

Explanation:

hope it would be helpful for u


9643903369k: are u sure na?
9643903369k: Review meetings are the managerial equivalent to ?
(A) Quality control
(B) Quality circle
(C) Quality index
(D) Quality curve
neeraj559145: yes
9643903369k: and can u ans for this also
neeraj559145: u can add in ask the question
neeraj559145: (b)
9643903369k: b for) quality circle??