while a does 1/3 piece of work b does 1/4 while b does 1/4 while 1/5 c does 1/6 in how many hours will c finish a work which a finish in 20 hours
Answers
Correct Question :- While A does 1/3 of a piece of work B does 1/4, while B does 1/5, C does 1/6; in how many hours will C finish a piece of work which A finishes in 20 hours ?
Solution :-
Case 1) :- While A does 1/3 of a piece of work B does 1/4 .
Since time is same in both .
→ (1/3) / A = (1/4) / B
→ A/B = (1/3) / (1/4)
→ A/B = (4/3)
So,
→ A : B = 4 : 3 { Efficiency ratio }
or,
→ A : B = 8 : 6
Case 2) :- while B does 1/5, C does 1/6;
Since time is same in both .
→ (1/5) / B = (1/6) / C
→ B/C = (1/5) / (1/6)
→ B/C = (6/5)
So,
→ B : C = 6 : 5 { Efficiency ratio }
then,
→ A : B : C = 8 : 6 : 5
Now ,Let efficiency of A , B and C is 8x units / hours , 6x units / hours and 5x units / hours respectively .
Then,
→ Time taken by A to finish the work = 20 hours
So,
→ Total work = Efficiency of A * Time taken = 8x * 20 = 160x units .
therefore,
→ Time taken by C to finish the same work = Total work / Efficiency of C = 160x / 5x = 32 hours (Ans.)
Hence, C will finish the same piece of work in 32 hours .
Learn more :-
Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...
https://brainly.in/question/21025557
Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...
https://brainly.in/question/14687371