why setting time test is performed on cement​

Answers

Answered by jkour0751
0

Answer:

Initial setting time test is important for transportation, placing and compaction of cement concrete. Initial setting time duration is required to delay the process of hydration or hardening. Final setting time is the time when the paste completely loses its plasticity.