Worker a takes 18 days to finish a job. Worker b takes 27 days to finish the same job. How long should it take for both a and b, working together to finish the same job?
Answers
Answered by
19
SOLUTION :
No of days taken by "A " to finish a job = 18 days
No of days taken by B to finish the same job = 27 days
Similar questions
Biology,
6 months ago
Music,
6 months ago
English,
6 months ago
Political Science,
1 year ago
Computer Science,
1 year ago
Science,
1 year ago
Social Sciences,
1 year ago
Math,
1 year ago