Math, asked by hibjitbarman8072, 10 months ago

Working 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days?

A) 10 B) 12 C) 16 D) 18

Answers

Answered by Avanimudabagil
0

Answer:

The answer is a option B