working 4 hrs a day,R can complete work in 12 days and working for 8 hrs in a day, A can complete work in 9 days,working 2 hrs in a day, how many days R and A together complete the work?
Answers
Answered by
0
Answer:
You can do like this. If this answer helps you plz follow me