working for 6 hours daily ,40 people can complete a work in 14 days .working for 8 hours daily ,if the work is 5o be finished in 7 days, how many people are needed tondo the same work?
Answers
Answered by
0
Answer:
60 people
Step-by-step
6×40×14/8×7=
6×40×14/56
240×14/56
3360/56
simplified=60
=60 people