working for eight hours daily ,40 people can dig the foundation of a building in 21 days. working for 10 hours daily ,if the work to be finished in 14 days ,how many people to do the same? please send its solution with ratio and proportion method. please send it sortly.
Answers
Answered by
0
i hope this will usful to u
Attachments:
Answered by
0
Answer:
48
Step-by-step explanation:
We are given that working for eight hours daily ,40 people can dig the foundation of a building in 21 days.
Case 1) Let be the work done by men , be the no. of men , be the no. of days taken to complete work and be the no. of hours per day .
So,
Now we are supposed to find working for 10 hours daily ,if the work to be finished in 14 days ,how many people to do the same
Case 2 ) Let be the work done by men , be the no. of men , be the no. of days taken to complete work and be the no. of hours per day .
So,
Hence working for 10 hours daily ,if the work to be finished in 14 days ,48 people to do the same