Math, asked by pratimapratham487, 1 month ago

working together 20 men of the same capacity can finish a job in 15 days. now 20 men start together on this job, but 10 of them leave after 10 days. how many more days remaining men take to finish the job?

Answers

Answered by prasanthikuchipudi
0

Answer:

10 more days

Step-by-step explanation:

Given,

working together 20 men of the same capacity can finish a job in 15 days.

20 men=1/15 days

now 20 men start together on this job, but 10 of them leave after 10 days.

20 men did 10 days of work

20 men=10/15

20 men=2/3 part work done by 20 men in 10 days

remaining work is 1-2/3=1/3

1/3 work has to be done by 10 men in how many days

let x be days

let 2p/3p work is done by 20 men in 10 days

20 men*10 days=2p-----(1)

10 men*x days=1 p ----(2)

by dividing Eq(1) by (2)

20*10/10*x=2p/1p

x=10 days