working together a b and c completes the work in 24 days after working together a left the work after 4 days .a and b completes remaining work in 30 days .how many days taken by c to completes the work alone
Answers
Answered by
2
Answer:
one days work of each of A,B and C is
1/24 =5/120 ,1/30=4/120 and 1/40=3/120 respectively
so that their one days work when all three work together is
(5/120)+(4/120)+(3/120)=12/120 =1/10 th part of the whole work
so they all together can complete the work in 120/12 =10 days
C left 4 days before means 4 x 1/10 = 4/10 part of work is left
A and B s one days work is 5/120 + 4/120 =9/120 th part
so they can complete whole the work in 120/9 days
and they can complete 4/10 th part of work in
4/10 x120/9 =16/3 days or 5+ (1/3) days
total work will be completed in 6+ 5+(1/3)=11+(1/3) days