Math, asked by sumanpattanayak6639, 1 year ago

Working together,rajeev and vikram can complete a piece of work in 48 days.Rajeev can complete the work alone in 64 days.Both of them worked together for 30 days and then rajeev left.How long will vikram take to complete the remaining work?

Answers

Answered by rishika79
5

Answer:

Step-by-step explanation:

This problem can be done using lcm concept

quantity of work to be done=lcm(64,48)=192units

work done by rajeev and vikram=192/48=4units/day

work done by rajeev =192/64=3units/day

so work done by vikram=4-3=1units/day

work done by rajjev and vikram in 30 days=30*4=120units

Remaining work to be done by vikram=12-120=72units

so time taken by vikram to complete 72 units=72/1=72days2 years ago

Hope it helps you....

Answered by 45mehul
2

first sort the array in nlgn and then its easy just take two pointers one pointing ats start index of array and one at the end of the array and start checking sum

like this

whwrw a is the integer array givcen

int *p;

int *q;

p=a;

q=a+n-1;

while(p!=q)

{

if(*p+*q==sum)

{printf("(%d,%d)\n",*p,*q);

p++;

q--;

continue;}

if(*p+*q<sum)

{

p++;

continue;

}

q--;

}

Similar questions