Math, asked by FsG11AJ, 11 months ago

Write correct answer only.Dont answer even if you don't know any one of them...
All the questions are completely shown in pic.
Don't spam or your answer will be deleted. ​

Attachments:

Answers

Answered by aditya967757
0

Answer:

1) 2 days

Step-by-step explanation:

A does 3/4 of the work in 12 days therefore, total no. of days is (4×12)/3. Now, no days required to do the 1/8 of the work will be 1/8×16 which will be 2.Hope it helps you.

Thank you.