write the formula used for perstage compation
Answers
Answered by
1
Answer:
The Percentage of completion formula is very simple. First, take an estimated percentage of how close the project is to being completed by taking the cost to date for the project over the total estimated cost. Then multiply the percentage calculated by the total project revenue to compute revenue for the period.
Answered by
0
The Percentage of completion formula is very simple. First, take an estimated percentage of how close the project is to being completed by taking the cost to date for the project over the total estimated cost. Then multiply the percentage calculated by the total project revenue to compute revenue for the period. Then derive the construction income by subtracting the cost from the period revenue.