(X + 10) workers can finish a piece of work in (X - 8) days. If the work is to be completed in 10 days, then number of extra workers required is 48. Find the value of X.
Answers
Answered by
1
Answer:
12.7
Step-by-step explanation:
Number of workers required to finish the work in (X-8) days = (X+10) workers
Number of workers required to finish the work in 1 day = (X+10)/(X-8) workers
Number of workers required to finish the work in 10 days= 10* (X+10)/(X-8) workers
48= 10X+100/(X-8)
48X-384=10X+100
38X=484