Math, asked by romirk4046, 11 months ago

X alone can do a piece of work in 15 days and y alone can do it in 10 days. x and y undertook to do it for rs.720. with the help of z they finished it in 5 days. how much is paid to z?

Answers

Answered by rakeshmohata
4
Hope u like my process
======================
Sorry if handwriting is bad
______________________
Hope this is ur required answer

Proud to help you
Attachments:
Answered by wifilethbridge
4

Answer:

Z's share is Rs.120

Step-by-step explanation:

X can complete work in days = 15

X can do a part of work in 1 day =\frac{1}{15}

Y can complete work in days = 10

Y can do a part of work in 1 day = \frac{1}{10}

They can do together a part of work in 1 day  =\frac{1}{15}+\frac{1}{10}

With the help of Z, they finish the work in 5 days.

With Z 1 day work = \frac{1}{5}

So, Z's 1 day work  = \frac{1}{5}-(\frac{1}{15}+\frac{1}{10})

                               = \frac{1}{30}  

Ratio of their 1 day work =  \frac{1}{15}: \frac{1}{10}:\frac{1}{30}

                                       = 2:3:1

Sum of ratios = 2+3+1=6

Z's share = \frac{1}{6} \times 720

               = 120

Hence Z's share is Rs.120

Similar questions