X alone can do a piece of work in 15 days and y alone can do it in 10 days. x and y undertook to do it for rs.720. with the help of z they finished it in 5 days. how much is paid to z?
Answers
Answered by
4
Hope u like my process
======================
Sorry if handwriting is bad
______________________
Hope this is ur required answer
Proud to help you
======================
Sorry if handwriting is bad
______________________
Hope this is ur required answer
Proud to help you
Attachments:
Answered by
4
Answer:
Z's share is Rs.120
Step-by-step explanation:
X can complete work in days = 15
X can do a part of work in 1 day =
Y can complete work in days = 10
Y can do a part of work in 1 day =
They can do together a part of work in 1 day =
With the help of Z, they finish the work in 5 days.
With Z 1 day work =
So, Z's 1 day work =
=
Ratio of their 1 day work =
= 2:3:1
Sum of ratios = 2+3+1=6
Z's share =
=
Hence Z's share is Rs.120