X and Y can complete a task in 15, 10 days respectively. After the two of them worked together for 3 days X joined Z instead of work. If all the work is completed in the next 4 days, how many days can Z alone complete the work?

Answers

Answered by shiwkishor
0

Step-by-step explanation:

work done by x and y in 3 days

= 3/15 + 3/10 = 1/2

Work done by x in 4 days

= 4/15

work done by Z in 4 days = 1/2 – 4/15 = 7/30

7/30 portion of work done in 4 days

he whole work will be done in 120/7 = 17 1/7 days.