x and y can complete a work in 12 days together. after working 4 days together, i left the job and third person z who's efficiency is 5/3 of efficiency of x, joins the work. the whole work is completed in 8 days. in how many days y can complete the whole work alone.
Answers
Answered by
5
Answer:
in 15 days
Step-by-step explanation:
hope it's your ans