X and Y can do a piece of work in 10 days and 6 days respectively they work together for 2 days and Y leaves the work. In how many days X will finish the remaining work?
Answers
Answered by
51
X and Y do a piece of work in 10 days and 6 days.
So,
And
Now,
Both X and Y work together for 2 days.
So,
We have to find that in how many days X will complete the remaining work.
From above calculations we find that Remaining work is 7/15 and X do a piece of work in 10 days.
So,
X complete the remaining work in 14/3 days.
Answered by
54
Answer:-
Explanation:-
Given:-
- x can do a piece of work in 10 days
- y can do a piece of work in 6 days
- Both x and y work together for 2 days and y leaves the work
To Find:-
The time taken by X to finish the work
Solution:-
Work done by X in one day =
Work done by Y in one day=
Given, both X and Y work together for 2 days
work done by X in 2 days = =
Work done by Y in 2 days = =
Work done by both X and Y in two days
Now, Y leaves the work
Work remaining :-
Time taken by X to do the remaining work
•••♪♡
Similar questions