Math, asked by ramasre671976, 19 days ago

X and Y can do a piece of work in 10 days and 6 days respectively they work together for 2 days and Y leaves the work. In how many days X will finish the remaining work?​

Answers

Answered by ankush026410
1

Answer:

4days 16 hours

Step-by-step explanation:

x=10

y=6

lcm-60

10x2-20

6x2-12

12+20-32

=28÷6

=4days 16h