X and y can do a piece of work in 20 days and 12 days respectively.X started the work alone and then after 4 days y joined him till the work completion. How long did the work last
Answers
Answered by
5
I hope it's help u...............
Attachments:
Answered by
2
The work lasts for 6 days
Step-by-step explanation:
X can complete work in days = 20
X 's 1 day work =
Y can complete work in days = 12
Y's 1 day work =
(X+Y)'s 1 day work =
X 's 4 days work =
Remaining work =
(X+Y) can complete work together in days =
(X+Y) can complete 16/ 20 work together in days =
The work lasts for 6 days
#Learn more:
A can do a piece of work in 34 days while B can do it in 46 days.A and B started the work and A left after working till 11 days.then B continued the work.after working for 6 days C joined B.C is twice plus 30% efficient than B.they worked for 4 days until completion of work and C leaves.how many days was the work completed?