X and Y together can complete a piece of work in 4 days. If X alone can complete the same work in 12 days. In how many days can Y alone can complete that work?
Answers
Answered by
2
Answer:
i have to solve
Step-by-step explanation:
Answered by
1
Answer:
8 days
Hope it's correct thank you ฅ'ω'ฅ