Math, asked by doddmanisapna4, 5 days ago

X and y together can complete a project in 6 days if x works alone on the project we will take 5 days less than y to complete the project alone​

Answers

Answered by XxMissPsychoxX
8

\huge\pink{\fbox{\tt{࿐Aɴѕωєя࿐}}}

A & B working together do work in 6 days.

A takes 5 days less than B.

Let B takes x

⇒A=x−5

 \frac{ 1}{x}  +  \frac{1}{x - 5}  =  \frac{1}{6}

 \frac{ x - 5 + x}{ {x}^{2}  - 5x}  =  \frac{1}{6}

12x - 30 =  {x}^{2}  - 5x \\  {x}^{2}  - 17x + 30 = 0 \\  {x}^{2}  - 15x - 2x + 30 = 0 \\ x(x - 5) -  2(x - 5) = 0 \\ (x - 2)(x - 5) = 0

⇒x = 12 \: or \: x = 15

As, x&lt;5     so x=15 \\ </p><p>then A=10 days &amp; \: B=15 days</p><p></p><p>

Hence, the answer is 10,15days.