Math, asked by dikshantjayant9042, 1 year ago

X and y together can complete a work in 27 days y and z in 36 days z and x in 54 days. In how many days will all of them together complete the work

Answers

Answered by bhagyashreechowdhury
6

Answer:

X and Y completes the work in = 27 days

Y and Z completes the work in = 36 days

Z and X completes the work in = 54 days

So,  

Work done by X & Y in 1 day = 1/27

Work done by Y & Z in 1 day = 1/36

Work done by Z & X in 1 day = 1/54

Work done by X, Y & Z together in 1 day  

= ½ * [1/27 + 1/36 + 1/54]  

= ½ * [(4+3+2)/108]

= ½ * [9/108]

= ½ * 1/12

= 1/24

Thus, X, Y & Z together will complete the work in 24 days.