X and Y together can do a piece of work in 6 days, while X alone can do it in 9 days. In how many days
can Y alone do the same work ?
Answers
Answered by
0
Answer:
x+y=1/6 or 54/6=9
x=1/9 or 54/9=6
one day work of y=1/6-1/9=1/18 or 9-6=3
no days y alone would take to complete the work = 1÷1/18=18days or 54/3=18days.
Answered by
0
Number of working days = Total work/Work done per day
LCM =18
Xand Y per day work=18/6
=3 units
X's per day work=18/9
=2 units
Y 's workper day=3-2
Y's =1 unit
Total Working days For Y=18/1
=18 days