Math, asked by jpmisra, 1 year ago

X and Y together do a certain piece of work in 8 days. if X does it alone and completes the work in 12 days . in how many days will Y alone complete the work ?​

Answers

Answered by Anonymous
4
\huge\textbf{Answer}

X and Y together do a certain piece of work in 8 days.

Work done by both (X and Y) in 1 day = \dfrac{1}{8} days

If X along complete the work in 12 days.

Then work done by X in 1 day = \dfrac{1}{12} days.

Now we have to find the work done by Y alone.

Work done by XY = Work done by X + Work done by Y

Work done by Y = Work done by XY - Work done by X

Work done by Y = \dfrac{1}{8} - \dfrac{1}{12}

= \dfrac{3\:-\:2}{24}

= \dfrac{1}{24} days

\textbf{Work done by Y alone is 24 days.}

jpmisra: thx
Anonymous: Welcome