X and Y together to a certain piece of work in 8 days . if x does it alone he completes the work in 12 days . in how many days will Y alone complete the work ?
Answers
Answered by
9
X and Y together do a certain piece of work in 8 days.
Work done by both (X and Y) in 1 day = days
If X along complete the work in 12 days.
Then work done by X in 1 day = days.
Now we have to find the work done by Y alone.
Work done by XY = Work done by X + Work done by Y
Work done by Y = Work done by XY - Work done by X
Work done by Y = -
=
= days
Answered by
1
X and Y together do a certain piece of work in 8 days.
Work done by both (X and Y) in 1 day = \dfrac{1}{8}
8
1
days
If X along complete the work in 12 days.
Then work done by X in 1 day = \dfrac{1}{12}
12
1
days.
Now we have to find the work done by Y alone.
Work done by XY = Work done by X + Work done by Y
Work done by Y = Work done by XY - Work done by X
Work done by Y = \dfrac{1}{8}
8
1
- \dfrac{1}{12}
12
1
= \dfrac{3\:-\:2}{24}
24
3−2
= \dfrac{1}{24}
24
1
days
\textbf{Work done by Y alone is 24 days.}Work done by Y alone is 24 days.
Similar questions