X can complete a job in 30 days. y can complete the job in 60 days. both work together along with z to complete job in 10 days . fine the share of z in a total of 6000 paid for work
Answers
Answer:
X can complete a job in 30 days. y can complete the job in 60 days. both work together along with z to complete job in 10 days . fine the share of z in a total of 6000 paid for work
Given:
X can complete a job in 30 days, Y can complete the same job in 60 days. Both X and Y along with Z complete the work in 10 days together. An amount of 6000 is paid for completing the project to all of them.
To Find:
The share Z has received in completing the work.
Solution:
1. It is given that X can complete a job in 30 days,
=> Work done by X every day = (1/30).
2. For the same job Y takes 60 days,
=> Work done by Y in 1 day = (1/30),
3. Let the work done by Z per day be denoted as z.
4. For 10 days,
- Work done by X = 10 x (1/30) = 1/3,
- Work done by Y = 10 x ( 1/60) = 1/6,
- Work done by Z = 10 x z = 10z.
5. Work done by X, Y, and Z together for 10 days completes the job. Hence,
=>,
=> 10z = 1 - (1/2),
=> 10z = 1/2,
=> z= (1/20).
6. The fractions of work done by X, Y, and Z for 10 days are (1/3), (1/6), (1/2). The payment received by Z will be,
=> Share of Z in the project = (fraction of work) x 6000,
=> Share of Z = 0.5 x 6000,
=> Share of Z = 3000.
Therefore, the share of z in a total of 6000 is 3000.