X can complete a work in 10 days and y can do in 15 days. if they are hired for 5 days to work together, what is the work that is left unfinished

Answers

Answered by GR44
1
Here's the answer.

Hope this helps. Please mark as brainliest and follow me!
Attachments:
Answered by prachikalantri
0

x can do \frac{1}{10} work in a day.

y can do \frac{1}{15} work in a day

Together=\frac{1}{10_{\times 3}} +\frac{1}{15_{\times 2}}  (1 day)

=\frac{5}{30}

=\frac{1}{6}

They work for 5 days

\therefore completed work=\frac{1}{6}\times 5

=\frac{5}{6}

\therefore unfinished work=1-\frac{5}{6}

=\frac{5}{6}

#SPJ2