Math, asked by tiwaridiksha673, 3 months ago

x can do a piece of work in 12 days and y can do the work in 20 days . They work together for 3 days and then x goes away. In how many days y finish the work​

Answers

Answered by prabhas24480
0

\huge{\fcolorbox{black}{grey}{\large{\fcolorbox{white}{black}{{\fcolorbox{grey}{purple}{❤AnSwEr❤}}}}}}

Let the required days be x.

A works for (x - 2) days, while B works for x days.

According to the question,

x−210+x20=1

2x- 4 + x = 20

3x = 24

x = 8 days

hope it helps....

Answered by KishanKumar0001
0

Step-by-step explanation:

X does the work in 20 days

=>In 1 day X will do 1/20 part of the work

=>In 3 days X will do 3/20 part of the work

Y does the work in 12 days

=>In 1 day Y will do 1/12 part of the work

=>In 3 days Y will do 3/12 i.e. 1/4 part of the work

Total work done after 3 days is :

 \frac{1}{4}  +  \frac{3}{20}  \\  =  \frac{8}{20 }  \\  =  \frac{2}{5} parts \: of \: total \: work

Remained work is

1 -  \frac{2}{5} \\  =  \frac{3}{5} parts \: of \: total \: work

So Y will take

 \frac{ \frac{3}{5} }{ \frac{1}{4 } }  \\   = \frac{3}{5}  \times  \frac{4}{1}  \\  =  \frac{12}{5}  = 2 \frac{2}{5} days

So total time = 3+2.4 = 5.4 days or 5 days 10hrs

Thanks

Thanks

Please Rate My Answer As Brainliest...

Similar questions