x can do a piece of work in 12 days and y can do the work in 20 days . They work together for 3 days and then x goes away. In how many days y finish the work
Answers
Answered by
0
Let the required days be x.
A works for (x - 2) days, while B works for x days.
According to the question,
x−210+x20=1
2x- 4 + x = 20
3x = 24
x = 8 days
hope it helps....
Answered by
0
Step-by-step explanation:
X does the work in 20 days
=>In 1 day X will do 1/20 part of the work
=>In 3 days X will do 3/20 part of the work
Y does the work in 12 days
=>In 1 day Y will do 1/12 part of the work
=>In 3 days Y will do 3/12 i.e. 1/4 part of the work
Total work done after 3 days is :
Remained work is
So Y will take
So total time = 3+2.4 = 5.4 days or 5 days 10hrs
Thanks
Thanks
Please Rate My Answer As Brainliest...
Similar questions