Math, asked by dhanasekartool, 10 months ago

x can do a piece of work in 18 days and y can do it 24 days. How much y get if they finish the work and earn Rs. 42,000.
A) Rs. 24,000
B) Rs. 18,000
C) Rs. 20,000
D) Rs. 22,000

Answers

Answered by RvChaudharY50
21

Gɪᴠᴇɴ :-

  • x can do a piece of work in 18 days.
  • y can do it 24 days.

Tᴏ Fɪɴᴅ :-

  • How much y get if they finish the work and earn Rs. 42,000. ?

ᴄᴏɴᴄᴇᴘᴛ ᴜsᴇᴅ :-

☛ The wages paid for any task has to be divided among the workers in the proportion to their contribution towards the completion of the task.

☛ In other words, the money earned by completing a piece of work has to be divided in the proportion of the work done by them.

☛ If the workers have worked for the same number of days, the money can be divided in the ratio of their efficiencies.

☛ Efficiency is inversely proportional to the time taken to complete a task.

Sᴏʟᴜᴛɪᴏɴ :-

→ Time Ratio :- x : y = 18 : 24 = 3 : 4

So,

Efficiency Ratio = x : y = 4 : 3.

Now, Given That, Both Earn Rs.42,000 Total.

Therefore ,

y gets = (3/7) of 42000

→ y gets = (3/7) * 42000

→ y gets = Rs.18000 (Ans.)

Hence, y gets Rs.18,000 Total after Finishing The work.

Answered by Aravind1401
0

Answer:Rs.18000

Step-by-step explanation:

X's 1 day's work = \frac{1}{18}

Y's 1 day's work = \frac{1}{24}

Ratio of wages of X and Y = \frac{1}{18} : \frac{1}{24}

                                              =4:3

Y's share = Rs.(42000 × 3/7 )= Rs.18000