Math, asked by UpadhyayGaurav1560, 9 months ago

X can do a piece of work in 40 days he works at it for 8 days and then y finished it in 16 days how long will together to complete the work in

Answers

Answered by devarudra97
1

they will complete the work in 13 1/3 days i.e 40/3

Similar questions