Math, asked by riteshsindhu88, 2 months ago

X can do a work in 3 days, Y does three times the same work in 8 days, and Z does five times the same work in 12 days. If they have to work together for 6 hours in a day, then in how much time can they complete the work?​

Answers

Answered by RituRani2000
2

you can take this example similar to your question:

If the total efforts needed to complete the job is A. Therefore capacity of X to work in one day is A/5..

of B = 2A/15 and

of C = 3A/7

total work done by all three together in one day = A/5+2A/15+3A/7= 16A/21

now question asks for the time taken if three work together for 8 hrs/day.

let us assume that the capacities given in the question are for 24 hrs working( though surprising)

therefore the desired answer = (21/16)* 24/8= 63/16 days.

Answered by soumiknayak9
0

Given:

X can complete the work in 3 days.

Y can do three times the same work in 8 days.

Z does five times the same work in 12 days.

Working hours per day = 6 hours

Formula used:

Efficiency = Total work/Total Time

Calculations:

Let the total work be 1 unit.

Time to complete 1 unit by X alone = 3 × 6 = 18 hours

Time to complete the 3 units by Y alone =  8 × 6 = 48 hours

Time to complete the 1 unit by Y alone = 48/3 = 16 hours

Time to complete the 5 units by Z alone =  12 × 6 = 72 hours

Time to complete the 1 unit by Z alone = 72/5 hours

Efficiency of X = 1/18 units/hour

Efficiency of Y = 1/16 units/hour

Efficiency of Z = 5/72 units/hour

Combined efficiency of X, Y and Z = (1/18) + (1/16) + (5/72)

⇒ (8 + 9 + 10)/144

⇒ 27/144 units/hour

Time to complete total work by X, Y and Z together

⇒ 1/(27/144)

⇒ 144/27 hours

⇒ 5 hours 20 minutes

∴ They can complete the work in 5 hours 20 minutes.

Similar questions