X can do ¼ of a work in 10 days, Y can do 40% of work in 40 days and Z can do 1/3 of work in 13 days. Who will complete the work first?
A. X
B. Y
C. Z
D. None of the above.
Answers
Answered by
10
Answer : C.
Whole work will be done by X in 10*4 = 40 days.
Whole work will be done by Y in (40*100/40) = 100 days.
Whole work will be done by Z in (13*3) = 39 days
Therefore, Z will complete the work first.
follow me !
Similar questions
Math,
6 months ago
Math,
6 months ago
India Languages,
1 year ago
Biology,
1 year ago
Social Sciences,
1 year ago