x can finish 2/3 of a work in 6 days and y can finish 3/4 of the same work in 9 days. they worked together for 2 days and then y left. the remaining work was done by x. how much time did x take to finish the remaining work?​

Answers

Answered by udgirkar67
0

Step-by-step explanation:

x can finish 2/3 of work in 6 days

x can finish 1 whole work in 6÷2/3= 6×3/2

= 9 days

x can finish 1/9 of work in day

y can finish 3/4 of work in 9 days

y can finish 1 whole work in 9-3/4 =9x4/3= 12 days

y can finish 1/12 part of work in 1 day

work done by X and y in 1 day

= 1/9 + 1/12 = 4+3/36 = 7/36

work done by x and y in 2 days = 2× 7/36

= 7/18

remaining work = 1-7/18 - 11/18

x oes 1/9 part of work in 1 day

dos 11/18 part of work in 9×11/18 - 11/2 =5 1/2 days

x does remaining part of work in 5 1/2 days

please follow me and mark me as brainliest