X does 25% of work in 20 days.Y joins with X and they together the remaining work in 15 days.Y alone can do the whole work in how many days
Answers
Answered by
2
Answer:
if x does 25% work in 20 days so 100% work is done in 80 days
let y do work in y days
1/y = 65/2000
Step-by-step explanation:
y do whole work in 30.77 days
Answered by
2
Answer:
X does 25% of work in 20 days.Y joins with X and they together the remaining work in 15 days.Y alone can do the whole work in how many days